Construction Schedule
TxDOT contracted with Tiseo paving to complete the $3 million project. Construction began July 19, 2010, and is estimated to be completed in August of 2011.
Road Closure
The first phase of the project includes the installation of box culverts. This requires closing the road to through traffic for an estimated four weeks from 9 a.m. on July 19, 2010, until 3 p.m. on Aug. 16, 2010.