| IH 10 (North Desert Blvd.) - El Paso County |
|
Reported: 3/19/2012 9:00:00 AM Expected to end: 5/31/2012 9:00:00 PM Beginning at: Artcraft Rd. Ending at: Transmountain Rd. Construction Condition - Westbound Lanes - - Frontage road only, main lanes are open. There will be left lane closures on North Desert Blvd. between Artcraft and Transmountain Rd. The closure will remain until the end of May 2012 this is a 24 hour closure(MST). |
| IH 10 (South Desert Blvd.) - El Paso County |
|
Reported: 3/19/2012 9:00:00 PM Expected to end: 5/31/2012 9:00:00 AM Beginning at: Transmountain Rd. Ending at: Isela Rubalcava Ave. Construction Condition - Eastbound Lanes - - MAIN LANES not affected. - Frontage road only, main lanes are open. There will be left lane closures Eastbound on South Desert Blvd. between Transmountain and Isela Rubalcava Ave. This closure will remain until the end of May 2012. This is a 24 hour closure (MST) |
| IH 10 - El Paso County |
|
Reported: 5/20/2012 9:00:00 AM Expected to end: 5/25/2012 4:00:00 PM Beginning at: Executive Overpass Ending at: Eastlake Interchange Construction Condition - East and Westbound Lanes - - MAIN LANES not affected. The East and westbound shoulders will be closed on I-10 between the Executive Overpass and the Eastlake Overpass. |
|
Reported: 5/20/2012 9:00:00 AM Expected to end: 5/25/2012 4:00:00 PM Beginning at: Downtown Exit Ramp Ending at: Eastlake Interchange Construction Condition - East and Westbound Lanes - - Alternating lanes closed. There will be Left and right lanes closure on Gateway West and Gateway East between the Downtown Exit Ramp and the Eastlake Interchange. |
|
Reported: 5/20/2012 9:00:00 PM Expected to end: 5/25/2012 5:00:00 AM Beginning at: Sunland Park Overpass Ending at: McRae Overpass Construction Condition - Eastbound Lanes - - Alternating lanes closed. Expect eastbound alternate right and left lane closures on I-10 between the Sunland Park Overpass and the McCrae Overpass. |
| SH 20 (Alameda) - El Paso County |
|
Reported: 1/21/2012 6:00:00 AM Expected to end: 6/1/2012 5:00:00 PM Beginning at: Boone ST. Ending at: Concepcion St. Construction Condition - East and Westbound Lanes - - Main lanes closed. ALAMEDA (SH 20) PROJECT: Traffic switch of the westbound and eastbound lanes will begin Saturday, January 21 at 6 a.m. The westbound lanes will be completely closed on Alameda Ave. from Concepcion St. to Boone St. and will continue closed through June 2012. The eastbound lanes will be switched to one eastbound and one westbound lane for traffic flow. |
|
Reported: 1/23/2012 9:00:00 AM Expected to end: 6/1/2012 4:00:00 PM Beginning at: Concepcion St. Ending at: Boone St. Construction Condition - East and Westbound Lanes - - All traffic reduced to one lane, two-way traffic control in place, be prepared to stop. ALAMEDA (SH 20) PROJECT: Westbound lanes will be completely closed on Alameda from Concepcion St. to Boone St. Reconstruction of the westbound lanes will be performed. Two way traffic on the eastbound lanes. |
| SL 375 (Americas Ave.) - El Paso County |
|
Reported: 5/21/2012 9:00:00 AM Expected to end: 5/25/2012 4:00:00 PM Beginning at: Socorro Overpass Ending at: Zaragoza Overpass Construction Condition - East and Westbound Lanes - - Alternating lanes closed. East and westbound right and left lane closures on LP 375 between the Socorro Overpass and Zaragoza Overpass including the Socorro Entrance Ramp. |
| SL 375 (Cesar Chavez Border Highway) - El Paso County |
|
Reported: 3/1/2012 6:00:00 AM Expected to end: 5/31/2012 Beginning at: 0.25 miles west of Padres Dr. Ending at: 0.25 miles east of Padres Dr. Construction Condition - Eastbound Lanes - - Exit ramp closed. - Entrance Ramp closed. - Follow the marked detour The eastbound Padres Exit Ramp and Padres Entrance Ramp will remain closed until further notice. Loop 375 traffic wanting to use Padres Dr. will need to exit at the eastbound Zaragoza Exit Ramp and turn around at the Zaragoza Dr. intersection to Loop 375 westbound to Padres Dr. Southbound traffic on Padres Dr. wanting to enter Loop 375 eastbound will need to travel westbound to the Yarbrough Dr. Exit Ramp, then turn around at the Yarbrough Dr. intersection onto Loop 375 eastbound. |
|
Reported: 3/1/2012 6:00:00 AM Expected to end: 8/1/2012 Beginning at: 0.25 miles west of Padres Dr. Ending at: 0.23 miles west of Zaragoza Rd. Construction Condition - Eastbound Lanes - - Right lane closed. The eastbound traffic on the Cesar Chavez Border Highway (Loop 375) has been shifted from the right lane onto the newly constructed center lanes, between Plant Rd. and Zaragoza Rd. Exit Ramp. At this time, there will be two lanes open for travel with occasional daily lane closures. |
|
Reported: 3/6/2012 9:00:00 AM Expected to end: 8/1/2012 Beginning at: 0.25 miles east of Yarbrough Dr. Ending at: 0.43 miles east of US 54 (Patriot Freeway) Construction Condition - Westbound Lanes - - Left lane closed. - Motorists should expect delays. - Travel lanes reduced to one lane. |
|
Reported: 3/6/2012 9:00:00 AM Expected to end: 8/1/2012 Beginning at: 0.43 miles east of US 54 (Patriot Freeway) Ending at: 0.25 miles west of Padres Rd. Construction Condition - Eastbound Lanes - - Left lane closed. - Motorists should expect delays. - Travel lanes reduced to one lane. |
|
Reported: 3/6/2012 9:00:00 AM Expected to end: 8/1/2012 Beginning at: 0.23 miles west of Zaragoza Rd. Ending at: 0.25 miles east of Yarbrough Dr. Construction Condition - Westbound Lanes - - Right lane closed. The westbound traffic on the Cesar Chavez Border Highway (Loop 375) will be shifted from the right lane onto the newly constructed center lanes between Zaragoza Entrance Ramp and Plant Rd. At this time, there will be two lanes open for travel with occasional daily lane closures. |
| SL 375 (JOE BATTLE) - El Paso County |
|
Reported: 5/1/2012 7:00:00 PM Expected to end: 5/31/2012 6:00:00 AM Beginning at: .5 MILES NORTH OF MONTWOOD Ending at: 1 MILE SOUTH OF MONTWOOD Construction Condition - North and Southbound Lanes - - Main lanes closed. - Alternating lanes closed. - Nighttime closure only. THERE WILL BE NIGHTLY ALTERNATING LANE CLOSURES BETWEEN THE MONTWOOD EXIT RAMP AND THE MONTWOOD ENTRANCE RAMP STARTING AT 7:00PM UNTIL 6:00AM. |
| SL 375 (JOE BATTLE EXIT) - El Paso County |
|
Reported: 5/1/2012 9:00:00 AM Expected to end: 5/31/2012 4:00:00 PM Beginning at: 5 MILE NORTH OF MONTWOOD Ending at: 1 MILE SOUTH OF MONTWOOD Construction Condition - North and Southbound Lanes - - Main lanes closed. - Alternating lanes closed. - Daytime closure only. WATCH FOR DAILY ALTERNATING LANE CLOSURES FROM 9:00AM TO 4:00PM BETWEEN THE MONTWOOD EXIT RAMP AND THE MONTWOOD ENTRANCE RAMP. |
| SL 375 (JOE BATTLE FRONTAGE ROAD) - El Paso County |
|
Reported: 5/1/2012 9:00:00 AM Expected to end: 5/31/2012 4:00:00 PM Beginning at: 1 MILE SOUTH OF MONTWOOD Ending at: .5 MILE NORTH OF MONTWOOD Construction Condition - North and Southbound Lanes - - Alternating lanes closed. - Daytime closure only. - Nighttime closure only. THERE WILL BE DAILY ALTERNATING LANES CLOSURES NORTHBOUND ON JOE BATTLE BLVD BETWEEN WINDERMERE AVE AND ZARAGOZA. ALTERNATING LANE CLOSURES SOUTHBOUND ON JOE BATTLE BLVD BETWEEN MONTWOOD AND THE MONTWOOD ENTRANCE RAMP. AND ALTERNATING LANES CLOSURES IN BOTH EASTBOUND AND WESTBOUND DIRECTIONS AT THE MONTWOOD/JOE BATTLE INTERSECTION. THE SOUTH TO NORTH TURNAROUND LANE WILL BE CLOSED THE ENTIRE MONTH OF MAY. |
| SL 375 (Purple Heart Blvd) - El Paso County |
|
Reported: 5/7/2012 6:00:00 AM Expected to end: 5/25/2012 4:00:00 PM Beginning at: Spur 601 Ending at: Montana Ave Construction Condition - Southbound Lanes - - Left lane closed. - Daytime closure only. Left lane closure Southbound at Mile Marker 32 for Overpass substructure construction operations on Purple Heart Highway between the Spur 601 and Montana Blvd. Daily closures from 6:00 AM to 4:00 PM. |
| SL 375 (Woodrow Bean/Transmountain) - El Paso County |
|
Reported: 5/21/2012 9:00:00 AM Expected to end: 5/25/2012 4:00:00 PM Beginning at: US-54 Ending at: BU-54 (Dyer) Construction Condition - Westbound Lanes - - Follow the marked detour WOODROW BEAN / TRANSMOUNTAIN (Loop 375) EXTENSION PROJECT: The following closures will be in place along Woodrow Bean/Transmountain (Loop 375) between Dyer St. (BU 54) and 1 mile west of US 54: Eastbound center median, East and westbound alternate lane closures, Shoulders, Alternate North and Southbound lanes at the intersection of Rushing and Woodrow Bean. The eastbound Emergency Exit Ramp at the base of Transmountain and Gateway South will be closed daily from 7 a.m. to 5 p.m. The following detour will be in place (nightly) 7 p.m. to 6 a.m.: Traffic traveling westbound on Woodrow Bean/TransMountain between Kenworthy Ave. and Gateway North will be detoured right on Kenworthy then to Fairbanks Dr. and then onto Gateway South. The Girl Scout Way Crossover continues closed until further notice. The Wal-Mart Crossover is permanently closed. Access to all the surrounding businesses will always remain open. |
| SL 478 (Dyer St.) - El Paso County |
|
Reported: 5/21/2012 9:00:00 AM Expected to end: 5/26/2012 4:00:00 PM Beginning at: US-54 Ending at: Paisano (US-85) Construction Condition - East and Westbound Lanes - - Alternating lanes closed. DYER ST. (Loop 478) MILL & INLAY PROJECT: Expect alternate left and right lane closures (east and westbound) at the Dyer/Pershing Intersection and the Dyer/Copia Intersection between US 54and Paisano (US 85). Day Closures: Monday May 21 through Saturday May 26 from 9:00 a.m. to 6:00 p.m. Night Closures: Monday Night May 21 through Friday May 25th from 6:00 p.m. to 6:00 a.m. the following morning |
| Conditions can change rapidly. No warranty of accuracy or completeness is expressed or implied. |